legal question Hi,I booked 1 bhk flat in 2018 in Thergaon Pune,Oak view residency project,as per agreement possession date was dec2019 also same date was in Maharera, builder failed to give possession on time I paid whole amount 40 lakh to builder,in feb builder extend possession date to Dec 2020 in Maharera without intimating ,in March due to Covid government extend further six months for possession, as per agreement I can ask interest for delay possession,or can I cancel booking as I unable to match emi and house rent due to deduction in salary.

legal answer from lawyer E00303568Dear client,
Send him notice through lawyer and file complain in consumer Court and claim heavy compensation.



Lawyer Detail

Talk to Lawyer

legal answer from lawyer E00320390There are already 4 complaints lodged against Oak view and its Director and this can be handled if FIR is lodged against the builder and the matter will be investigated by EOW branch. After the complaint they enter into a memorandum of Understanding between with the property owners and refund their amount on monthly basis or either hand over the possession.



Lawyer Detail

Talk to Lawyer

legal answer from lawyer E00307724IF U HAVE AS PER THE AGREEMENT ANY RULES U CAN CANECL IT OR STOP THE INTEREST AS THE COVID GO WIHT THAT



Lawyer Detail

Talk to Lawyer

legal answer from lawyer E00313895Dear Sir, You can have both the option. Either claim the interest or take a refund with the interest. The total choice is yours. You need to see the factors i.e. return on investment.
You need to first send the legal notice to builder for any one of the below mention option. In case of non response from the builder the you have to file online complaint with the RERA tribunal.
In case of any further advice please connect with me.



Lawyer Detail

Talk to Lawyer

legal answer from lawyer E003216271. You can complaint to Real Estate (Regulation and Development) Act, 2016 authority and get is registration cancelled on the ground of unfair trade practice and fraudulent trade practice if the project is registered under Real Estate (Regulation and Development) Act, 2016.
2. If the project is not registered under Real Estate (Regulation and Development) Act, 2016 u can file complaint in Consumer Forum and get your money back with interest.
3. You can make bank party in all these to establish your bon fide.
4. Police complaint for cheating and dishonest misappropriation of property.
5. Under Real Estate (Regulation and Development) Act, 2016 he is required to deposit a part of advance intimate them not to release it to the builder.
Apart from these there are other options. For further clarification you may contact me through Pathlegal. Hit the like button if the advice is useful to you.



Lawyer Detail